  operation instructions
  1.1Check the products from the last process step.return the off-
quality products to the last process.
  1.2Material preparation1:the products must be well prepared before 
water dipping .
  1.3material preparation 2:a metal door may need to dip two times, 
each with different pattern, so preparation had to be made on the door 
for such purpose.
  1.4take a metal door, which needs to be coated on double side with 
different pattern, for example, the uncoated side should be close with 
a nylon net.
  1.5make a nylon closure:the closure is made of 300 mesh nylon net, 
the size of the net is a little larger than the door dimensions, round 
the net are attached (by sewing)with magnetic bars.
  1.6Close the uncoated side of the door with above mentioned nylon 
net.Note:The above measure is only an example to close the uncoated 
area of a metal door, anyway you have to find a solution for your 
particular products, use adhesive type to seal the uncoated area is 
also simple and very popular.
  1.7Fix the metal door to a jig frame, the jig frame,together with the 
metal door, maybe hanging from the ceiling or an iron structure, the 
jig frame must be lowered down below the water surface.try several 
times until you are satisfactory with the dipping procedure.
  1.8if the size of the products is very small, you have to arrange the 
small pieces in the jig frame , fix the pieces  tightly with fixtures 
or clips attached to the jig frame,the pieces must fix tight not to 